Problem
Abandoned creosote plant that stopped production in the 1940’s left a legacy of creosote leaching into an adjacent creek. A two step process of clean up and remediation of the streambank restored the natural bank and eliminated any leaching potential. Heavy, flashy storms battered the sandy banks eroding, in some areas, over 15 feet of streambank threatening a newly installed well head monitor.

Project Background
Dating to the turn of the century this creosote plant was used to make telephone poles and rail road ties. An extensive system of monitoring wells, removal of contaminated soils, and the use of organoclay to remove oil from water and to seal any potential of petrochemical leaching was utilized in this clean up of the site.

 

Solution
To revegetate the streambank and control continual erosion, Envirolok was utilized to face the highly eroded stream and protect monitoring wells that were installed as part of the clean up effort. PermaMatrix® Biotic Soil Amendment was installed over the Envirolok system to restore the biological function of the streambank. PermaMatrix is a combination of organics and biochar that greatly enhances the establishment and diversity of native plants. Sunmark environmental provided the Certified Installers to work with local contractors and was able to complete this job in 4 working days.

Permits Engineering
Provided by Premier Environmental of Marietta GA. Pantheon Group, prime contractor with Southern Specialty Services providing construction leadership. Sunmark Environmental coordinated the environmentally-sensitive solution by working with all the stakeholders, engineers and general contractors.

 

 

Environmental Review
Community Reaction, “This is such a difference, what use to be an ugly, polluted site is now restored for everyone that lives here”.

 

 

 

Project Fact Sheet

Contractor Installer:
Pantheon Group Inc
1880 West Oak Parkway
Building 100, Suite 106
Marietta, GA 30062

Southern Specialty Services, Inc.
8424 Wallace Tatum Road
Cumming, GA 30028

Certified Installer:
Sunmark Environmental Services, LLC
12775 NE Marx St., Portland OR 97230

 

Engineering Provided By:
Premier Environmental Services, Inc.
1880 West Oak Parkway
Building 100, Suite 106
Marietta, GA 30062
United States
Contact information provided on request